Tooling fabrication process and XPUMP PCBA DVT2 updates

Posted by Peng Lee (Creator)
26 likes

Dear Friends,

In the past two weeks we have been focusing on tooling fabrication and PCBA DVT (design verification test). XPUMP team and vendors are working hard together to bring XPUMP into the next stage of manufacturing---product verification test, or PVT, next week. PVT will be the last stage of trial run, or pilot run of 100 units, before mass production. Regarding the tooling fabrication we are very glad to share some snapshots of our work here for you. 

 Tooling Fabrication 

  • Vendor is working on the mold with machinery
 project video thumbnail
Replay with sound
Play with
sound
  • Male and female molds of top and bottom cover
Male mold of top and bottom cover
Male mold of top and bottom cover

 

Female mold of top and bottom cover
Female mold of top and bottom cover
  •  Sound effect keys and LED light guide
Female mold of sound effect key and LED light guide
Female mold of sound effect key and LED light guide
  •  Volume key and slide switch key
Male mold of volume key and slide switch key
Male mold of volume key and slide switch key
  •  Electrical Discharge Machining process
EDM process
EDM process

 

PCBA DVT2 (Design Verification Test)

  • PCB (printed circuit board) itself before SMT process
PCB
PCB
  • PCBA (printed circuit board assembly) after SMT process

 

PCBA bottom view
PCBA bottom view

 

PCBA top view
PCBA top view

Please stay tuned with our coming updates. We will have a lot more to share in the following weeks. Many Thanks! 

Best Regards,

XPUMP team  

----------------------------------------------------------------------  

親愛的朋友們:

過去的兩周,工程團隊與供應商專注在試產兩大部分:模具開立DVT 試產,下周我們即將邁入下一個階段PVT, pilot production 100組,這也會是試產的最後階段,用來確定所有生產流程與品質檢驗標準,這次的更新提供模具開立過程中的影片,各組件模具與DVT2的電路板讓大家了解XPUMP需要經歷的量產準備流程,接下來的一個月會有更多細節跟大家分享,請大家留意之後的進度更新了喔!

XPUMP Team

SK, jake, and 24 more people like this update.